FDOT to repair or replace Livingston Rd’s. private wall!

I reached Dan Kowel’s office (our commissioner, Dist. 4) to express our concerns about the hurricane damage and received the reply below.  I will monitor the progress and keep you posted!

Hi Ken,

The (inspection/investigation/maintenance) of the privacy wall on the roadway of concern is actively being addressed.  Following a thorough inspection, the Road, Bridge, & Stormwater Management (RBSM) inspector has confirmed that repairs are necessary.  We are currently finalizing a contract to have a structural engineering firm to evaluate and provide repair and/or replacement options for the privacy wall.

Our team is committed to completing this project as promptly as possible while ensuring high-quality repairs. We will continue to provide updates as progress is made.

Reason to be placed on hold:  Finalizing Design Consultant Contract

Here are the anticipated remaining activities/schedule:

  • Contract Administration Review (QC):  1 – 3 Days
  • Procurement Process:  1-2 weeks (14 Days)
  • Board Approval: 1 month (30 Days)
  • Pending Procurement’s decision, the WO, which is based on a term (annual) contract, may not need Board approval
  • PO Req/NTP:  1-2 weeks (7 – 14 Days)
  • Design Process:  6 Months (180 Days)
  • Procurement/Construction Process:  4-6 months (120 – 180 Days)
  • Construction (pending recommendations):  3-6 Months (90 – 180 Days)

For further inquiries or to report a Roads or Stormwater emergency, please call (239) 252-8924. This line is monitored 24/7 to ensure a prompt response to urgent issues.

Thank you.

Marshal Miller
Division Director – Road, Bridge & Stormwater Maintenance
Office:  239-252-8924 (24-Hours)