FDOT to repair or replace Livingston Rd’s. private wall!
I reached Dan Kowel’s office (our commissioner, Dist. 4) to express our concerns about the hurricane damage and received the reply below. I will monitor the progress and keep you posted!
Hi Ken,
The (inspection/investigation/maintenance) of the privacy wall on the roadway of concern is actively being addressed. Following a thorough inspection, the Road, Bridge, & Stormwater Management (RBSM) inspector has confirmed that repairs are necessary. We are currently finalizing a contract to have a structural engineering firm to evaluate and provide repair and/or replacement options for the privacy wall.
Our team is committed to completing this project as promptly as possible while ensuring high-quality repairs. We will continue to provide updates as progress is made.
Reason to be placed on hold: Finalizing Design Consultant Contract
Here are the anticipated remaining activities/schedule:
- Contract Administration Review (QC): 1 – 3 Days
- Procurement Process: 1-2 weeks (14 Days)
- Board Approval: 1 month (30 Days)
- Pending Procurement’s decision, the WO, which is based on a term (annual) contract, may not need Board approval
- PO Req/NTP: 1-2 weeks (7 – 14 Days)
- Design Process: 6 Months (180 Days)
- Procurement/Construction Process: 4-6 months (120 – 180 Days)
- Construction (pending recommendations): 3-6 Months (90 – 180 Days)
For further inquiries or to report a Roads or Stormwater emergency, please call (239) 252-8924. This line is monitored 24/7 to ensure a prompt response to urgent issues.
Thank you.
Marshal Miller
Division Director – Road, Bridge & Stormwater Maintenance
Office: 239-252-8924 (24-Hours)